Location: Juneau, AK | SMC Contract: $11,000,000

This project consisted of constructing a new 120,000 sq/ft two story high school in Juneau Alaska. Manpower was the largest issue on this project as there are only so many tradesman available in SE AK; we were able to overcome this issue by prefabricating much of the work which allowed us to begin working long before any dirt was moved or steel was erected.